Stormwater and Sanitary Project Updates:

  1. Pine/Avon Stormwater Improvement Project Update 07.14.17

    Pine/Avon Stormwater Improvement Project: This week excavation efforts continued in the new stormwater basin.  2 full days of excavation took place which equates to 600 loads (6,000 total cubic yards) leaving the site.  Additionally the new 48”...

  2. Madison Early Childhood Education Center Stormwater Improvement Project Update 7.3.17

    The contractor has finished sodding the parkways on Washington Street and Bryan Street.  Some minor curb replacement is underway on Washington Street, and the final surface lift of asphalt will be installed on Washington Street on Monday, July 3rd.

  3. Harrison Stormwater Improvement Project Update 7.3.17

    Installation of the concrete wall cap is nearly complete in the west half of the basin, and installation of the cap is underway in the east half. Once the cap install is complete the final grading and landscaping will be completed.

  4. Pine Street / Avon Road Stormwater Improvement Project Update 7.3.17

    Excavation of the detention basin is now 50% complete.  The contractor will be installing underdrain in the bottom of the basin next week along with continuing excavation.  On First Street, the underground contractor plans to begin installing sewer...