Wet Weather Control Facility Construction Update

Posted on March 14, 2016 at 11:34 AM by Amanda Stuber

Boller Construction is continuing work with the assembly of the mixing system components that are inside of the 2 million gallon storage tank. The tank structure is completed.

Tank under construction 2

Tank near completion

During the course of this winter, Boller Construction has continued to work at the Saylor & Jackson station preparing the site for the generator replacement and building demolition.
 Work is anticipated to continue in full force near the end of the month.  Future work at the Saylor and Jackson Lift Station includes sewer relocations and connections, building extension, and pump installation.

This project is anticipated to be substantially completed and operational by Summer 2016. 

For more information on the project, please see project details on our Sanitary Projects page.