Apr 19

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.19.19

Posted on April 19, 2019 at 2:54 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-19-19

Due to poor soil conditions near the church parking lot, the contractor has concentrated on installing the 60-inch storm sewer parallel to Butterfield Road.  To help with the soil conditions in the area near the parking lot, dewatering wells have been installed.  It is anticipated dewatering operations will take 10-14 days to eliminate enough ground water to allow the remaining storm sewer pipe to be installed.

SESMP Phase 1 - 4.19.19



  

 

 

 


Apr 05

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.05.19

Posted on April 5, 2019 at 2:00 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-05-19

The underground boring contractor completed the second (smaller) casing under Butterfield and the forcemain was installed within the casing pipe.  This completes the major underground improvements on the north side of Butterfield.  Pipe installation of the 60-inch storm sewer from the detention basin to the storm sewer previously bored under Butterfield at Bryan Street continues; it is anticipated that all of the 60-inch pipe installation will be finished by the end of April.
   

SESMP Phase I - 4-5-19

 
















 

Mar 22

Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 03-22-19

Posted on March 22, 2019 at 3:43 PM by Barbara Petrucci

The contractor has continued the installation of the 60-inch storm sewer from the detention basin towards Butterfield Road.  At the same time, the boring contractor has successfully completed the boring of the 60-inch storm sewer under Butterfield Road.  The boring contractor has removed his equipment from the boring pit to allow a large 8-foot diameter storm sewer structure to be installed.   Once the 60-inch storm sewer work in this area is completed, the boring contractor will be back to bore a 24-inch casing for the forcemain installation under Butterfield Road.

SESMP I 3-22-19