Aug 28

SESMP Phase I Update August 27, 2018

Posted on August 28, 2018 at 2:25 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase I

The contractor recently finished installing the 48” storm sewer in the centerline of Bryan up to the intersection of Jackson this week. The crew is now replacing a portion of the sanitary sewer between Van Buren and Jackson. There will be one more new 18” storm sewer main to be installed between Van Buren and Jackson to replace the existing sewer that was removed, and the crew will then begin replacing all damaged and lead water service lines that were exposed during sewer installation. In early-to-mid September the roadway restoration on Bryan, Jackson to Harrison, will begin and include curb repairs and roadway restoration.


SESMP Phase I Update 8.27.18A
Jul 25

SESMP Phase I Update July 25, 2018

Posted on July 25, 2018 at 12:12 PM by Barbara Petrucci

Southwest Elmhurst Stormwater Mitigation Project-Phase I

Underground storm sewer and utility work continues at the intersection of Bryan and Harrison. Work in this area is being prioritized to minimize impacts to Bryan Middle School when classes resume in August. The underground work in the intersection should be completed soon followed by the operation proceeding north along Bryan.SESMP Phase I Update 7-25-18aSESMP Phase I Update 7-25-18