Mar 22

Southwest Elmhurst Stormwater Mitigation Project - Phase II - 03-22-19

Posted on March 22, 2019 at 3:46 PM by Barbara Petrucci

The contractor completed final testing of the pumps and float sensors for the storm water pump station.  Training for City staff is being scheduled in the next few weeks and once completed; the city will take over operations of the pumping station.  When this occurs the project will be considered completed.

SESMP Phase II Update 3-22-19

Feb 25

Southwest Elmhurst Stormwater Mitigation Project - Phase II Update 02-22-19

Posted on February 25, 2019 at 11:39 AM by Barbara Petrucci

Work this week included final electrical connections and installation of the pumps.  The pumps are set to be turned on late next week for their first trial run and for testing.  After the pumps are operating per the design then City staff will be trained on the operations of the pumps.

SESMP Phase II Update 2-22-19
Nov 09

Southwest Elmhurst Stormwater Mitigation Project - Phase II - Update 11.09.18

Posted on November 9, 2018 at 2:16 PM by Barbara Petrucci

The site work on the project is now nearly complete with all concrete, pavement, fencing, and restoration installed. The only remaining item on the project is the fabrication of the permanent pump which is expecting to be installed in the next 2-3 weeks. No other work is anticipated before then, and the basin is now functional and able to take storm water if needed during any large rain events.
PHASE II 11.9.18