Aug 25

Madison Early Childhood Education Center Stormwater Improvement Project 08.25.17

Posted on August 25, 2017 at 8:40 AM by Barbara Petrucci

The project is now substantially complete and operational. Grass is growing in the stormwater basin south of Madison Early Childhood Center and Washington Street has been repaved.

Crescent_Cambridge Stormwater Improvement Update Photo 07 23 17
Jul 03

Madison Early Childhood Education Center Stormwater Improvement Project Update 7.3.17

Posted on July 3, 2017 at 1:00 PM by Barbara Petrucci

The contractor has finished sodding the parkways on Washington Street and Bryan Street.  Some minor curb replacement is underway on Washington Street, and the final surface lift of asphalt will be installed on Washington Street on Monday, July 3rd.

Madison Early Childhood Update Photo 6-30-17
Jun 09

Madison Early Childhood Education Center Stormwater Improvement Project Update 06.09.17

Posted on June 9, 2017 at 11:56 AM by Barbara Petrucci

Washington Street (north of Madison Ave):  The contractor has completed installation of all underground utilities and completed installation of new concrete curb and driveway aprons.  Over the next week or two the contractor is scheduled to remove the remainder of the asphalt pavement on Washington Street, install new street lighting conduits, restore the parkways with sod, and repave the street.

Madison School Detention Basin:  The contractor has completed installation of underdrain system and finished building the retaining wall in the bottom of the basin.  Over the next week or two the contractor is scheduled to finish the basin with topsoil and seed, install sod in the parkways, repave the adjacent intersections, and install fence around the perimeter of the basin.

Currently the basin is “on-line” and can accept 6.25 AC-FT of stormwater during large rain events; providing flood reduction benefits to the homes on Washington between Madison and McKinley.



Madison Early Childhood Update Photo Update 6 9 17