York/I-290 Stormwater Improvement Project Update 08.24.17

Posted on August 24, 2017 at 4:20 PM by Barbara Petrucci

The project is now substantially complete and operational.  The pump station has been installed and tested.  The Contractor has punchlist items to address, including re-seeding the bottom of the basin and re-installing erosion control stone.

York_I-290 Stormwater Improvement Project Update Photo 07 20 17





Jul 14

York/I-290 Stormwater Improvement Project Update 4.3.17

Posted on July 14, 2017 at 2:32 PM by Barbara Petrucci

York/I-290 Stormwater Improvement Project Update 4.3.17

The control panel for the permanent lift station is still on backorder. Once the panel is available, it will be installed along with the remaining mechanical components of the lift station.  Until then, the temporary pump remains in place to drain the basin when it fills during storm events.

York_I-290 Stormwater Improvement Project Update Photo 4.3.17
Dec 12

York/I-290 Stormwater Improvement Project Update 12/12/16

Posted on December 12, 2016 at 2:41 PM by Barbara Petrucci

Lift station components are still being fabricated at this time.  The contractor is anticipating that the components will be ready for installation in January 2017.  Installation of the pump station mechanical equipment is anticipated to take several weeks.  The detention basin is currently online and functional with the use of temporary pumps.