Stormwater and Sanitary Project Updates:

  1. Saylor/Swain/Vallette Project Update 07.24.20

    The demolition of the 4 houses on Swain has been finalized with all the foundations and driveways removed, along with leveling off of the site. Also completed this week was the installation of the large box culverts on Crescent Ave. The storm sewer...

  2. Saylor/Swain/Vallette Project Update 07.16.20

    Currently the contractor has begun installing the box culverts under Crescent Avenue this week.  These twin 10’ x 8’ box culverts will be ran from Swain Avenue to Saylor Avenue along Crescent and will provide complimentary detention volume to the...