Home

Stormwater and Sanitary Project Updates:

  1. Saylor/Swain/Vallette – Project Update - 09.28.20

    The utility work in front of the four lots has been completed and the restoration of this area has begun.  The concrete work has begun with curbs and sidewalks being poured.  The ground above the StormTrap system has been final graded and the seeding...

  2. Saylor/Swain/Vallette – Project Update - 09.21.20

    A major milestone was achieved this week when the contractor completed the installation of the StormTrap chambers.  The final connection of the 54-inch storm sewer into the StormTrap system will occur next week with the delivery of a special order...

  3. Saylor/Swain/Vallette – Project Update - 09.11.20

    Installation of the StormTrap chambers continued this week along the former Swain Avenue residential lots and it is anticipated all the chambers will be installed by the end of next week.  Once the StormTrap System is completely installed, the final...

View All