Stormwater and Sanitary Project Updates:

  1. Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04.05.19

    Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 04-05-19 The underground boring contractor completed the second (smaller) casing under Butterfield and the forcemain was installed within the casing pipe. This completes the major...

  2. Southwest Elmhurst Stormwater Mitigation Project - Phase II - 03-22-19

    The contractor completed final testing of the pumps and float sensors for the storm water pump station.  Training for City staff is being scheduled in the next few weeks and once completed; the city will take over operations of the pumping station. ...

  3. Southwest Elmhurst Stormwater Mitigation Project - Phase I Update 03-22-19

    The contractor has continued the installation of the 60-inch storm sewer from the detention basin towards Butterfield Road.  At the same time, the boring contractor has successfully completed the boring of the 60-inch storm sewer under Butterfield...