Home

September 2017

S M T W T F S
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
View All

Stormwater and Sanitary Project Updates:

  1. Pine/Avon Stormwater Improvement Project Update 08.25.17

    All underground utility work has now been completed for the project. The new relief storm sewer piping is “online” and ready in the event of a flood situation.  All concrete restoration (curb, sidewalk, and driveway aprons) has been completed....

  2. Washington Street Stormwater Improvement Project Update 08.25.17

    Installation of the underground concrete vault is complete.  The vault is online and will take water if a flooding event occurs.  At present, the lift station is incomplete.  The contractor is ordering the correct pumps and control panel.  If a...

  3. Madison Early Childhood Education Center Stormwater Improvement Project 08.25.17

    The project is now substantially complete and operational. Grass is growing in the stormwater basin south of Madison Early Childhood Center and Washington Street has been repaved.

  4. Crescent/Cambridge Stormwater Improvement Project 08.25.17

    The project is now substantially complete and operational.  Grass is growing in the stormwater basin in York Commons Park and the sluice gate is functional.  The project came in under budget and was completed on time.

View All